Attending the event were Pham Gia Tuc, Politburo member and Standing Deputy Prime Minister; Tong Thi Phong, former Politburo member and former Standing Vice President of the National Assembly (NA); Tran Huy Tuan, member of the Party Central Committee and Secretary of the Ninh Binh provincial Party Committee; leaders of ministries and agencies, Vietnam Electricity (EVN), and the provinces of Lai Chau, Dien Bien and Ninh Binh.
Representing Son La province were Hoang Van Nghiem, member of the Party Central Committee, Secretary of the provincial Party Committee and head of the provincial delegation to the NA; Lo Minh Hung, Standing Deputy Secretary of the provincial Party Committee and Chairman of the provincial People's Council; Nguyen Dinh Viet, Deputy Secretary of the provincial Party Committee and Chairman of the provincial People's Committee; and Cha A Cua, Deputy Secretary of the provincial Party Committee and President of the provincial Vietnam Fatherland Front Committee.
The project, invested in by Xuan Thien Ninh Binh Co., Ltd., received in-principle approval from the Son La provincial People's Committee under Decision No. 2266/QD-UBND dated August 30, 2026. It will be implemented across Muong Bang and Muong Coi communes, covering more than 425 hectares, with total investment of nearly 28 trillion VND (1.08 billion VND) and a designed capacity of 1,200 MW from four turbines.
The first phase, scheduled for 2027-2030, will develop 900 MW, while the remaining 300 MW will be added during 2031-2032.
Upon completion, the plant is expected to generate approximately 1.5 billion kWh of electricity annually, helping stabilise the northern power system. It is also projected to contribute around 1 trillion VND to the provincial budget each year and create jobs for 2,400 workers during construction and 350 employees during operation.
To facilitate the project's groundbreaking, Son La has prioritised site clearance. To date, Muong Bang commune has completed the inventory of land, assets and crops belonging to 70 households, individuals and organisations, covering a total area of 70.86 hectares within the site clearance area for Phase I and the groundbreaking ceremony venue, fulfilling 100% of the plan.
Speaking at the groundbreaking ceremony, the Chairman of the provincial People’s Committee acknowledged the coordination of ministries and agencies, local authorities and the investor. He commended Muong Bang commune for its site clearance efforts and local residents for their support for the project.
He also called on provincial departments, agencies and localities to work together to address difficulties, while urging the investor and contractors to mobilise resources and accelerate construction, ensuring quality, occupational safety and environmental protection. Son La province pledged to accompany the investor and create favourable conditions for the project to be carried out on schedule and in compliance with regulations.
On this occasion, Xuan Thien Group donated 5 billion VND to Son La province's Social Welfare Fund to help improve living conditions for disadvantaged households./.