Secretary of the provincial Party Committee Hoang Van Nghiem and the working delegation present gifts to the construction team of the primary and secondary boarding school in Chieng Son commune.
For the primary and secondary boarding school project in Chieng Son commune, construction has reached approximately 75% completion. To date, nine of the 10 three-storey buildings have completed the third-floor roof slab, while eight have finished the structural framework. The kitchen and dining hall have completed their structural works, and the multi-purpose hall has achieved around 50% of its structural construction.
Secretary of the provincial Party Committee Hoang Van Nghiem and the working delegation inspect the construction progress of the primary and secondary boarding school in Long Sap commune.
Đối với dự án xây dựng Trường nội trú liên cấp Tiểu học - THCS Lóng Sập, đến nay, dự án đạt tiến độ khoảng 49,1%. Khối nhà 3 tầng đã thi công xong sàn mái 5/13 khối; đang xây tường và trát trong nhà, khối lượng ước đạt 40%; khối nhà 2 tầng đã thi công xong phần dầm, sàn tầng 2; nhà đa năng đã đắp móng xong, chuẩn bị thi công cột; nhà bếp đang thi công lắp dụng cốp pha dầm, sàn tầng mái, xây tường ngăn…
For the school project in Long Sap commune, overall construction progress has reached approximately 49.1%. Five of the 13 three-storey buildings have completed their roof slabs. Meanwhile, the two-storey building has completed the installation of beams and the second-floor slab. Foundation works for the multi-purpose hall have been completed.
Secretary of the provincial Party Committee Hoang Van Nghiem and the working delegation present gifts to the construction team of the primary and secondary boarding school in Long Sap commune.
Secretary Nghiem stressed that the projects carry great political significance for education and training, as they will provide students in border areas with the best possible conditions for learning and personal development. Therefore, ensuring both construction quality and schedule is of paramount importance.
The provincial Party leader urged the investors, contractors and relevant agencies to uphold the highest sense of responsibility, promptly resolve all outstanding issues, complete the necessary procedures, and mobilise maximum manpower and equipment.
He called for the adoption of scientific and efficient construction measures, with a determination to complete the projects on schedule and ensure quality standards and workplace safety, so that the schools can be put into operation in time for the start of the new academic year.