Meeting discusses options for site clearance for CT.03 expressway

Deputy Secretary of the provincial Party Committee and Chairman of the provincial People’s Committee Nguyen Dinh Viet chaired a meeting on November 25 to discuss land recovery and site clearance plans for the Moc Chau – Son La – Dien Bien Expressway (CT.03)'s section running through Son La province.

An overview of the meeting to discuss land recovery and site clearance plans for the Moc Chau - Son La - Dien Bien Expressway (CT.03)'s section in Son La province.

The hybrid meeting saw the attendance of members of the provincial Party Committee’s Standing Board, Vice Chairpersons of the provincial People’s Committee, leaders of provincial departments and agencies, and representatives of Chieng Coi ward and the communes of Mai Son, Chieng Mung, Chieng Mai, Muong Chanh and Muoi Noi. 

A leader of the traffic construction investment project management board speaks at the meeting.

The CT.03 expressway section through Son La province is expected to stretch 179.5 km and require around 2,230 hectares of land, including 325.53 hectares of forest land subject to procedures for conversion to other purposes.

The project is estimated to affect 4,968 households and individuals and 32 organisations. It will include 26 concentrated resettlement sites for around 920 households and require the relocation of nearly 600 graves. In addition, approximately 749.5 hectares of land are expected to be acquired for dumping sites, with a capacity to accommodate around 99 million cu.m of excavated materials. About 102 hectares will be used for construction roads and bypasses, including the upgrading, improvement and expansion of around 63 km of existing roads.

Vice Chairman of the provincial People’s Committee Nguyen Minh Tien speaks at the meeting.

Participants focused their discussions on addressing difficulties and obstacles related to the project alignment, interchanges, underpasses for local residents, dumping sites, construction roads and resettlement.

Chairman of the provincial People’s Committee Nguyen Dinh Viet delivers remarks at the meeting.

Addressing the meeting, Viet asked departments, agencies and localities to accelerate site clearance, with an aim to complete preliminary land inventories and determine land origins before March 15, 2027, thereby paving the way for the first construction package to start no later than April 30, 2027.

Commune- and ward-level People’s Committees were tasked with accurately inventorying land and assets, proactively carrying out site clearance, reviewing resettlement needs and arranging resettlement areas with synchronised infrastructure to ensure safety and stable living conditions and livelihoods for affected residents.

The Department of Agriculture and Environment was assigned to take the lead in developing a unified site clearance process for the entire route through 18 communes and wards, while strengthening inspections, providing guidance and promptly resolving difficulties related to documentation and administrative procedures./.