Following the Ministry of Industry and Trade’s Official Dispatch No. 9413/BCT-DL dated November 6, 2026, requesting a review of and proposals for urgent power generation projects, the provincial Department of Industry and Trade completed its review and advised the provincial People’s Committee to issue Official Dispatch No. 9059/UBND-THKT on November 18, submitting the list to the ministry.
The list comprises 22 solar power projects with a combined capacity of 1,928 MW. Of these, three projects with a total capacity of 460 MW are already included in the revised Power Development Plan VIII; five potential projects with a combined capacity of 285 MW are identified in the provincial master plan; and 14 projects, totalling 1,183 MW, are proposed for additional inclusion in the power plan. The projects are expected to be developed across 12 communes and wards.
Major projects include the 400-MW Moc Chau solar power plant, the 350-MW Son La 1.1 floating solar power project, the 350-MW MSS Muong Gion solar power project and the 150-MW Muong La 17 solar power project.
The review found that Son La has favourable solar energy potential thanks to its high solar irradiation, with a reference PVout index of 1,381 kWh per kWp per year, providing a basis for research and development of renewable energy projects.
On investment preparations, locations and land areas have been identified for many projects, with initial assessments also conducted of their land clearance prospects. Grid connection plans are being studied and proposed for individual areas, including the construction or expansion of substations and transmission lines to accommodate the projects.
Under the proposed schedule, most projects aim to complete investment, achieve grid connection and begin commercial operation in the fourth quarter of 2027.
Concluding the meeting, Viet asked the Department of Industry and Trade to take the lead in coordinating the process. Once the Ministry of Industry and Trade issues its official response to the proposed list of urgent projects, the department should proactively engage with investors and work with relevant agencies and local authorities to review and provide comprehensive information on each project's location, scale and land requirements, while promptly addressing obstacles related to planning, land use and investment procedures.
Investors were urged to work closely with local authorities during site surveys and project location assessments. Communal and ward authorities were asked to focus on land inventory and determining land origins, prepare site clearance plans and step up public communication to build consensus and facilitate the early handover of land for project implementation.
Relevant departments and agencies were instructed to coordinate proactively, within their respective mandates, to guide and assist local authorities and investors in completing the necessary procedures, ensuring consistency and coordination throughout implementation and accelerating the progress of all 22 projects./.
You have 500/500 characters left
Please enter 5 or more characters!!!