Under Vietnam’s road network master plan for 2021-2030, with a vision to 2050, the Hoa Binh-Moc Chau Expressway is designed to meet highway standards, with a maximum speed of 80 kph, four lanes and a 22m-wide roadbed. The section running through Son La province is approximately 32.3 km long, passing through Van Ho and To Mua communes and Van Son ward. The component project has a total investment of 4.118 trillion VND (160.28 million USD).
Construction activity is currently in full swing across the project site. At Package No. 28, covering the Km74+500–Km85+300 section and including 10 bridges, contractors have mobilised 354 workers, 210 pieces of machinery and equipment, and 18 construction teams.
Do Van Ha, site commander of Tu Lap Construction Company, representing the contractor consortium, said the package had recorded 295 billion VND in completed work, equivalent to 25% of its contract value. The company is mobilising additional manpower and equipment and coordinating construction across all work items, targeting 90 billion VND worth of workload in November and 82 billion VND in December 2026.
At Package No. 27, covering the Km63+500–Km74+500 section and comprising eight bridges, the contractor consortium is maintaining 16 construction teams, with 271 workers and 126 pieces of machinery and equipment. Completed work has reached about 271 billion VND, or 25% of the contract value.
Trinh Ngoc Vinh, a technical officer at Bac Trung Nam Company, representing the consortium, said heavy rainfall and complex geological conditions at several locations had affected construction progress. To overcome these challenges, the contractors are concentrating manpower and equipment on accelerating work, targeting 74 billion VND worth of construction in November and a further 74 billion VND in December.
At Package No. 26, covering the Km53–Km63+500 section and including 10 bridges, the Son Hai - Company 479 consortium is operating 13 construction teams, with 262 workers and 120 pieces of machinery and equipment. The value of completed work currently stands at around 183 billion VND, equivalent to 16.6% of the contract value. Contractors are targeting 62 billion VND worth of workload in November and 66 billion VND in December 2026.
Alongside efforts to accelerate construction, the project investor is working to resolve outstanding difficulties, expedite the inspection and acceptance of completed work, and speed up payments to ensure public investment disbursement targets are met.
Hoang Manh Thang, deputy director of the provincial Transport Infrastructure Construction Investment Project Management Board, said total capital allocated to the project had exceeded 2.359 trillion VND, of which more than 1.892 trillion VND had been disbursed or advanced, representing approximately 80%. Disbursement for construction packages alone had exceeded 1.675 trillion VND.
Of the more than 843 billion VND allocated under the 2026 capital plan, the project had disbursed over 463 billion VND as of November 12, equivalent to 55%. A further 380 billion VND must be disbursed by year-end to fulfill the annual target.
However, the project continues to face several obstacles. About 2 km of the route requires an expanded land clearance area in line with construction design drawings. Some planned spoil disposal sites and construction access roads cannot proceed under the original plans because of their impact on local residents and land-use planning. As a result, eight replacement spoil disposal sites and five additional access roads must be arranged.
In addition, approval procedures for land clearance plans at several locations remain incomplete, delaying site handovers for construction. The construction capacity of some contractors is also limited and has yet to meet schedule requirements.
In response, the management board is coordinating with relevant departments, agencies and local authorities to resolve land clearance issues and complete procedures for additional spoil disposal sites and access roads.
It is also strengthening progress inspections and supervision, urging contractors to mobilise resources and accelerate construction. It is simultaneously expediting the acceptance and payment of completed work, with the aim of disbursing 100% of allocated capital before December 31, 2026.
At a working session with the project investor and contractors on November 12, Nguyen Dinh Viet, Deputy Secretary of the provincial Party Committee and Chairman of the provincial People's Committee, instructed the management board and supervision consultants to strengthen coordination and promptly address difficulties involving spoil disposal sites and construction access roads.
He also called for strict monitoring of the overall project schedule, as well as the progress of individual construction packages and contractors. Particular attention should be given to accelerating Phase 2, which involves upgrading the road from two lanes to four.
With decisive direction from provincial authorities, coordinated efforts by relevant departments and local administrations, and the commitment of the project investor and contractors, work on the Hoa Binh-Moc Chau Expressway is being sped up, with a focus on resolving bottlenecks, accelerating construction and ensuring public investment disbursement.
The project is an important step toward completing the northwestern region's transport network, creating momentum for socioeconomic development, trade and tourism in Son La province once the expressway is completed./.